UKSC/2009/0048

RTS Flexible Systems Limited (Respondents) v Molkerei Alois Müller Gmbh & Company KG (UK Production) (Appellants)

Judgment given

Case summary


Case ID

UKSC/2009/0048

Parties

Appellant(s)

Molkerei Alois Müller Gmbh & Company KG (UK Production)

Respondent(s)

RTS Flexible Systems Limited

Issue

Whether the parties entered into a contract following the expiry of the letter of intent.

Facts

The appellant is a well known leading European dairy product supplier. The respondent specialises in the supply of automated machines for packaging and product handling in the food and consumer goods industry. The appellant used manual labour to re-package its product and wishes to automate the process. The parties, for good commercial reasons, decided to start work before the terms of the contract between them had been agreed on the basis that, ultimately, terms would be finalised. No contract was ever signed as contemplated.

Judgment appealed

Full Judgment details


Judgment date

10 March 2010

Neutral citation

[2010] UKSC 14

Judgment summary

10 March 2010

Procedural Judgment details


Judgment date

21 July 2010

Neutral citation

[2010] UKSC 38

Appeal


Justices

Hearing dates

Full hearing

Start date

2 December 2009

End date

3 December 2009

Watch hearings


2 December 2009 - Morning session

Watch the archived video.

2 December 2009 - Afternoon session

Watch the archived video.

3 December 2009 - Morning session

Watch the archived video.

3 December 2009 - Afternoon session

Watch the archived video.

Change log

Last updated 16 April 2024

Back to top

Sign up for updates about this case

Sign up to receive email alerts when this case is updated.